Workspace > PD-19 Reduce, Reuse and Repurpose Materials

Criterion Details

PD-19 Reduce, Reuse and Repurpose Materials

PDF IconDownload as pdf

Project Development Scorecard

  • Paving
  • Rural Basic
  • Urban Basic
  • Rural Extended
  • Urban Extended
  • Custom Core

Goal

Reduce lifecycle impacts from extraction and production of virgin materials by recycling materials.

Sustainability Linkage

Triple Bottom Line

Reducing and reusing materials supports the environmental and economic principles of the triple bottom line by reducing the consumption of raw materials, reducing landfill waste, and encouraging cost savings.

Background & Scoring Requirements

Background

This criterion focuses on reducing and reusing materials while PD-20: Recycle Materials focuses on efforts to recycle materials per the descriptions and definitions provided below.

When pavements are originally constructed, the best materials available at the time are usually sourced and used during construction. As resources diminish, that often means that the best materials available for reconstruction are already in place in the existing infrastructure. In addition to reducing waste, recycling pavements allows us to reclaim the best materials that were originally available for construction.

Programs for waste reduction in the United States have generally taken on the concept of the 3Rs: reduce, reuse, and recycle. For the purposes of this criterion, as well as to PD-20: Recycle Materials, the key terms are defined as follows:

  • “Reducing” is used in this tool to refer to processes that reduce the need for virgin paving and structural materials. Examples include soil stabilization methods to reduce the need for structural backfill or to reduce the required thickness of a new pavement or overlay; pavement preservation technologies that extend the life of existing pavements and reduce the need for new materials; bridge preservation technologies that extend the life of existing bridges and reduce the need for new structures and materials; retrofitting existing bridge structures to reduce the need for new structures and materials; or processes that incorporate existing pavement structures into new pavement structures (such as crack-and-seat and rubblization) to reduce the need for new materials and avoid the transportation of the existing used materials which would otherwise be removed from a project.
  • “Reusing” is the reuse of a material or by-product from another industry for a new function in a transportation application. Examples of the beneficial use of industrial by-products include the incorporation of materials such as coal ash, fly ash, foundry sand, slag, asphalt shingles, construction and demolition materials, or other materials into a transportation project. These reused materials replace traditional materials with similar properties in specific applications. The reuse of these materials should assure that the engineering properties of the final product or mixture are equal to or better than obtained from using traditional materials, and that their economic value is demonstrated in accordance with the FHWA Recycling Policy. Reused materials provide environmental benefit by reducing the unnecessary landfilling of these materials. With proper engineering, these materials can be successfully incorporated into transportation applications and provide economic value to our projects.
  • “Recycling” is the use of old materials for a new and similar use in a transportation application, or the salvaging and reprocessing of previously used materials from other transportation applications into a new transportation project. See PD-20: Recycle Materials for examples.
  • “Retrofit” is defined as the addition of new features or technology to an older or existing facility. For INVEST purposes, a project would include retrofit components in order to reinforce structures to become more resistant and resilient to the forces of natural hazards and other environmental factors such as aging and weathering. It involves the consideration of changes in the mass, stiffness, damping, load path, and ductility of materials, as well as radical changes such as the introduction of energy absorbing dampers and base isolation systems.
  • “Existing pavement material” is defined as all material within the project limits in the existing pavement structure (including surfacing and base material). This includes travelled lanes and shoulders, and pavement structures for physically separated bicycle and pedestrian pathways.
  • “Existing structural material” is defined as all material within the project limits in existing non-pavement structures such as bridges (including overpasses), retaining walls, and stormwater infrastructure, such as vaults, pipes, and culverts. All existing structural materials include their foundations, for which volumes may be difficult to estimate. Where actual weights are not available, reasonable estimates may be used or volume may be estimated. To compute volume of hollow structural sections such as prefabricated members or corrugated steel, estimate the mass of the material and adjust for material density to determine volume. Note that for typical reinforced concrete sections, the steel does not need to be separated from the composite section for purposes of volume calculations and a composite density may be used.

Scoring Requirements

Implement one or more of the methods listed below. Points for different scoring requirements are cumulative; however, this criterion shall not exceed a total of 12 points.

Requirement PD-19.1

2-4 points. Pavement Preservation

Perform pavement preservation activities such as crack sealing, chip sealing, slurry sealing, microsurfacing, or thin ACP overlays that extend the remaining service life of pavements. This scoring requirement applies to pavement preservations and not rehabilitation or reconstruction activities. FHWA’s ACTION Pavement Preservation Definitions Memo1 defines pavement preservation as "a program employing a network level, long-term strategy that enhances pavement performance by using an integrated, cost-effective set of practices that extend pavement life, improve safety and meet motorist expectations.”

Points are awarded based on increase in remaining service life per Table PD-19.1.A.

TABLE PD-19.1.A POINTS AWARDED FOR PAVEMENT PRESERVATION ACTIVITIES

1 More than 10 years is considered rehabilitation and isn’t eligible for this scoring requirement.

Requirement PD-19.2

1-3 points. Reduce Pavement Materials

Reduce the amount of new pavement materials needed through soil stabilization methods to reduce the required thickness of a new pavement or processes that incorporate existing pavement structures into new pavement structures. Points are awarded per Table PD-19.2.A based on the percentage of pavement area treated. The area treated is calculated based on the entire area of existing pavement materials that are preserved or reconstructed.

Soil stabilization methods may include the use of geosynthetics (geogrids and fabrics) to reduce the thickness of aggregate required for stabilization of subgrade; the use of geosynthetics to reduce the thickness of aggregate above the geosynthetics that would have been required for structural support when subgrade soils are susceptible to pumping and base course intrusion; the use of portland cement and/or cementitious by-product materials for soil stabilization for pavement construction, if it can be demonstrated that this process will reduce the use of natural aggregate (virgin aggregate or material hauled from off-site source) use for stabilization; other chemical stabilization; and fractured slab techniques, including crack-and-seat, and rubblization.

TABLE PD-19.2.A POINTS AWARDED FOR REDUCING PAVEMENT MATERIALS

Requirement PD-19.3

2-4 points. Bridge Preservation

Perform bridge preservation activities such as deck overlays, crack sealing, joint sealing, removing channel debris, lubricating bearings, cathodic protection, electrochemical chloride extraction and cleaning, and painting that extend the remaining service life of bridges. This scoring requirement applies to bridge preservations and not rehabilitation or reconstruction activities. For definitions and examples of bridge preservation, see the FHWA Bridge Preservation Guide2. Points are awarded based on increase in remaining service life per Table PD-19.3.A.

TABLE PD-19.3.A POINTS AWARDED FOR BRIDGE PRESERVATION ACTIVITIES

Requirement PD-19.4

1-3 points. Retrofitting Bridges

Retrofit existing bridge structures to reduce the need for new structures and materials. This could include methods such that improve or add: stainless steel wire mesh composites, full height steel jackets, elastomeric bearings, steel restrainer cables, shear keys, fiber reinforced polymers wraps, shape memory alloy devices, metallic and viscoelastic dampers, or pipe seat extenders. Points are awarded based on increase in remaining service life per Table PD-19.3.A above.

Requirement PD-19.5

1-3 points. Repurpose Pavements or Structures

Reuse existing pavements, structures, or structural elements for a new use by repurposing them for a use that requires equal or less loading. The purpose of this scoring requirement is to maintain and leverage existing pavements, structures, and structural elements for new uses where possible instead of using new materials (as long as the existing elements meet the performance requirements of the new use). One method is to maintain existing pavements when new alignments are proposed and use the existing pavement for a new use, such as realigning a highway but maintaining the old one as a frontage road, cycle path track, or multiuse path. Another method is to convert existing pavement to a different use, such as converting parking to travelled lanes (or vice versa) or converting pavement to multiuse paths or plazas.

Pavement to be repurposed shall not be processed or moved in any way; it shall remain in-place. Points are awarded per Table PD-19.5.A based on the percentage of existing pavement material (by area) reused and repurposed calculated based on the entire area of existing pavement materials included in the project.

TABLE PD-19.5.A POINTS AWARDED FOR REUSING AND REPURPOSING PAVEMENTS IN PLACE

Requirement PD-19.6

1‐3 points. Reuse Industrial By‐Products

Scoring for this requirement is based on the following, cumulative elements:

  • Requirement PD-19.6a

1 point. Use By-Products for Pipe Bedding or Backfill

Using foundry sand or other industrial by-products in pipe bedding and backfill.

  • Requirement PD-19.6b

2 points. Use By-Products in Roadway Elements

Reuse industrial by-products in pavement materials, ancillary structures, and other roadway elements. These could include one or more of the following: coal ash, fly ash, foundry sand, slag, tires, asphalt shingles, and construction and demolition materials.

Requirement PD-19.7

1 point. Recycling and Reuse Plan

Develop and implement a project-specific plan for the innovative reuse of waste materials other than the methods listed in PD-19.1 through PD-19.6.

Resources

The following resources are referenced in this criterion and consolidated here:

  1. FHWA, ACTION Pavement Preservation Definitions Memo, http://www.fhwa.dot.gov/pavement/preservation/091205.cfm
  2. FHWA, Bridge Preservation Guide, http://www.fhwa.dot.gov/bridge/preservation/guide/guide.pdf

Case Studies & Criterion Examples

Western Federal Lands - Annual Sustainability Award Process Utilizes INVEST: The Western Federal Lands Highway Division (WFL) within the Federal Highway Administration uses the INVEST Project Development (PD) module to score, rank, and select the recipient of its Annual Sustainability Award. Starting in 2012, WFL instituted an Annual Sustainability Award to better market and showcase WFL sustainability efforts. During the first year, WFL compiled a list of 17 eligible (under-construction or recently constructed) projects including new construction and rehabilitation projects. As part of the scoring process, WFL met with each of the project managers to discuss the scope of the projects and identify sustainability features. After some projects were removed from the list due to their lack of sustainability elements, WFL staff evaluated the remainder of the projects using the Rural Extended Scorecard for the INVEST PD module.

Western Federal Lands - Going-to-the-Sun-Road Rehabilitation Project: The Going-to-the-Sun Road (Sun Road) is the first American roadway designated both a National Historic Landmark and a National Civil Engineering Landmark. Going-to-the-Sun Road is the only road through the heart of Glacier National Park in Montana. It was completed in 1932, and it is the only road that crosses the park, going over the Continental Divide at Logan Pass. Sun Road has more than 475,000 vehicles traveling it during peak visitor season from June to October, or about 3,500 vehicles per day. The Western Federal Lands Highway Division (WFL) within the Federal Highway Administration used the INVEST Project Development (PD) module to evaluate the Sun Road Rehabilitation Project. Stand out criteria included PD-03: Context Sensitive Project Development, PD-07: Habitat Restoration, PD-18: Site Vegetation, PD-19: Reduce and Reuse Materials, and PD-28: Construction Quality Control Plan.

TxDOT - Embedding INVEST in Contracting for the Corpus Christi Harbor Bridge: The Texas Department of Transportation (TxDOT) used INVEST during the procurement process for the Harbor Bridge Project in Corpus Christi. TxDOT’s request for proposals (RFP) required that bidders describe how their proposal would meet a “Platinum” rating on the INVEST PD module and a “Silver” rating on the INVEST OM module. The sustainability score, along with price and other factors, was part of the total score for selecting among the four bidders. This provided a strong incentive for bidders to achieve high sustainability at low cost. The winning bidder committed to a range of sustainability practices that will bring tangible benefits to the community.

Arizona DOT - Using INVEST to Integrate Sustainability: The Arizona Department of Transportation (ADOT) decided to use all three modules of INVEST – System Planning, Project Development, and Operations and Maintenance – to help the agency meet its sustainability goals across the transportation life cycle.  ADOT used INVEST to integrate and advance existing sustainability efforts and to push forward new efforts.  INVEST’s comprehensive sustainability framework and criteria helped ADOT institutionalize sustainability across the agency and with local partners through inclusion in manuals, trainings, and awards.  This case study focuses on ADOT’s use of the Project Development module.

Ohio DOT - George V. Voinovich Bridge/Cleveland Innerbelt Corridor : When building the largest bridge project in its history, the Ohio Department of Transportation (ODOT) turned to INVEST to make sure they made this massive project as sustainable as possible. ODOT replaced the Cleveland Innerbelt Bridge on I-90, now called the George V. Voinovich Bridge in two phases – the first was construction of the westbound bridge, completed in 2013; the second phase, design and construction of the eastbound bridge, began in 2014 and finished in 2017. ODOT used FHWA’s sustainability self-assessment tool, INVEST, to score the first phase to see if the project was meeting its goals. ODOT found the process so valuable that for the second phase of the project they included sustainability, as measured by INVEST, as one of the criteria for scoring contractor proposals for the design-build contract. This provided a strong incentive for bidders to incorporate sustainability while keeping costs competitive. In fact, the winning bidder committed to an “INVEST Platinum” level of sustainability with a bid $19 million below the ODOT engineer’s estimate.

Scoring Sources

The project is considered to have met this criterion if the requirements above can be reasonably substantiated through the existence of one or more following documentation sources (or equal where not available):

  1. Calculations showing the remaining service life of pavements or bridges expected before the project and after, and clearly demonstrating an extended service life as a result of the treatments applied.
  2. Calculation of the percentage pavement area treated, including the area of pavement treated and the existing pavement area preserved and retrofitted.
  3. The approved mix design for the pavement materials.
  4. Recycling and Reuse Plan.